TSC Magma Commercial Deployer Feedback

This page is WIP

Introduction

As TSC works on developing the roadmap for Magma development over future quarters, we want to solicit and incorporate feedback from companies doing commercial deployments of Magma. This feedback can come in 2 forms:

  • Responses to short survey via email (discussed in TSC 5/2/22)

  • Review and rankings of proposed roadmap items (TBD)

To facilitate the collection of this feedback, we use the below table which captures the commercial deployments of Magma with some attributes. 

Company Name

Deployment Start Date

Current Number of Active Subs

Current Number of Active Sites

Projected Number of Subs

( in 12 months)

TSC Contact Owner

Company Name

Deployment Start Date

Current Number of Active Subs

Current Number of Active Sites

Projected Number of Subs

( in 12 months)

TSC Contact Owner

FreedomFi

February 2020

500

5600

20k

Joey Padden

Viasat

September 2021

170

5

TBD

Joey Padden

InsistNet

August 2021

700

50

5k

Joey Padden

Radtonics Customers

Mar 2021 - May 2022

5525

439

56k

@Shubham Tatvamasi

Wavelabs Customers

Jan 2021-June 2021

2500-3200

15-43

20K( 250 sites planned) to 25K

@Yogesh Pandey

























  • Wavelabs Customers

    • Pain Points (deployment, operation)

      • Open bugs – data counting, QoS etc.

      • The number of subscribers per AGW.

    • Feature Gaps (Including Security Gaps)

      • Data accounting, QoS rate limiting, SMS, DPI, & more

      • Scaling UE Count per AGW, throughput/line rate.

  • FreedomFi Customers

    • Pain Points:

      • FeG Stability (Gy/Gx over medium latency links)

      • Roaming interface scalability (S8 inbound)

      • NMS bugginess (incomplete features, errant/stale data presented)

      • Lack of operations level documentation / UI interfaces

      • AGW SW upgrade using APT makes snowflakes

    • Feature Gaps

      • inter AGW handover

      • Outbound roaming 

      • Scalable inbound roaming

      • CDRs/TAP for roaming settlement 

Survey Questions

Below is a proposed email template TSC members can use to reach out to Magma deployers. 

-------------------------------------------------

Dear <blah>,

The Magma Technical Steering Committee is developing a feature roadmap to guide development efforts in the Magma community. As an operator deploying Magma for commercial services we seek your feedback on three key questions.  

Deployment Metrics:

  • Deployment start date:

  • Current number of active subs:

  • Current number of active sites:

  • Projected number of subs in 12 months:

  • Magma version(s) in deployment:

What are the pain point you experience in deployment, operation, or development of your magma network?

What feature gaps have you observed in Magma and how do they impact your business?

Is security up to your needs?

Please respond with your answers to above by May 13th. 

Best Regards, 

Magma TSC